工程造价外文翻译外文文献英文文献公路工程变更原因分析及其对工程造价的影响.doc

上传人:精*** 文档编号:826785 上传时间:2023-09-05 格式:DOC 页数:9 大小:41KB
下载 相关 举报
工程造价外文翻译外文文献英文文献公路工程变更原因分析及其对工程造价的影响.doc_第1页
第1页 / 共9页
工程造价外文翻译外文文献英文文献公路工程变更原因分析及其对工程造价的影响.doc_第2页
第2页 / 共9页
工程造价外文翻译外文文献英文文献公路工程变更原因分析及其对工程造价的影响.doc_第3页
第3页 / 共9页
工程造价外文翻译外文文献英文文献公路工程变更原因分析及其对工程造价的影响.doc_第4页
第4页 / 共9页
工程造价外文翻译外文文献英文文献公路工程变更原因分析及其对工程造价的影响.doc_第5页
第5页 / 共9页
点击查看更多>>
资源描述

1、Highway engineering change reason analysis and cost of the project of influenceAbstract: in the implementation stage because of highway engineering design factors, environmental factors, the influence of various engineering changes happened is more common, combining with engineering practice, this p

2、aper discusses the causes and engineering change of project cost.Keywords: engineering change, Reason, CostDue to the highway project period, long, long line, so broad in construction of various causes by the engineering change is inevitable. Engineering change could lead to increase of construction

3、 cost or time limit of the owner and the contractor, between the claim will claim and the cost of the project.Owner of change and the causes of the costAnd when the owner change engineering bidding of construction conditions of commitment. SanTongYiPing referred to in the preceding paragraph, the en

4、gineering tight finish, delay purpose will increase the contractors settlement fee, but little impact on total cost, the owner or project quantity change projects. Increase the project content or quantity, will increase the cost, Project content or cancel or reduce the number will reduce cost, but m

5、ay affect the use function of engineering, because the owner with agreements for the existence of incomplete, or in the contract when division, can increase content of missing the contract cost, and the owners requirements, and shorten delivery of finished ahead of the original contract period, inve

6、st more in construction unit cost of manpower and material resources, to increase, and improve the design standard requirement owner, beautiful Angle from security requirements of engineering structure change type, elevation, baseline, location, size and strength, make cost increase, and the owner t

7、o change in the construction organization design has approved the construction plan, cost increase, and the owner of the contract with the owner of the materials or equipment supply for the category and quantity, cause cost increase or decrease, and the owner of the contract specifies unreasonable,

8、can make the cost is increasedThe design of change and the causes of the costThe design adopts the new standard, new technology, new technology, to replace the original design of the project, and put to use more favorable for owner reduce project cost, the depth of the design documents, cannot satis

9、fy the relevant provisions of the relevant design phase of engineering change and requirements, cost increase or decrease, and when designing units in the preliminary design to fully consider the network planning, and in local government and related departments (e.g., environmental protection, water

10、 conservancy, electricity, gas, communication, navigation, etc.) and the requirements of the project, the main structure change shape and size change etc, make the cost increase, and design personnel errors or omissions caused engineering change. Due to the two SanShen school system to implement the

11、 change that cost is increased, Unit, uncoordinated cooperation between designers, or the highway facilities with the principal part of the project design, cause sync job change, make cost increase, and the design drawing not timely delivery time delay, provide, construction, make the cost compensat

12、ion shutdown caused by increased.Tthe contractor to change and cause the influence. CostThe contractor is unable to perform the contract or cant completely, the contractor shall take remedial measures proposed change, this kind of change of engineering cost, can increase by contractor burden loss, t

13、he contractor has been approved changes when bidding of construction project, this kind of change of cost, but almost no effect for the contractor may save construction cost, and the contractor for construction is convenient, or to shorten the construction period, or to reduce the investment of cons

14、truction, and puts forward such reasons, and more economical and reasonable, optimizing design scheme, this kind of change if owner recognized, can reduce the construction cost, also can reduce the cost of the owner and the contractor, mutually beneficial, According to the contract, the contractor c

15、ouldnt finish, engineering construction contract extension, the owner may terminate the contract terms, according to the content of construction contract in whole or in part, by the contractor, this kind of other changes generally does not make owner cost increase, but will make the contractor under

16、 loss, due to the contractor technology or management of the error caused by engineering change, this kind of change to the contractor, the owner may claim generally do not increase the cost, stipulated in the contract, the contractor change by owner procurement materials, using other kinds of mater

17、ials, and therefore model brand damage by contractor, unless the owner to approbate, generally do not add costthe supervisor of change and the causes of the costSupervision by the owner, commissioned by the cause of the change of the owner or expenses directly influence the cost. 1 and supervision e

18、ngineer in order to coordinate the contractors operation, or section of this project contractors to coordinate with relevant departments or units where the relations of production, easy cause engineering change caused by increased cost. the site supervision engineers in actual situation in the contr

19、act and the technical specification for the design, according to local modification and perfect or by design, this kind of change unit may cause increased cost. and supervision engineers work and coordination ability damage caused by lack of rework, engineering cost change work. and supervision engi

20、neer proposed optimization design or construction, the design optimization or contractor agree, can reduce engineering changes caused by the project cost.The environment factors and impact on the cost of changeEngineering geology unknown or insufficiency in design, engineering cost increased to. and

21、 highway engineering construction projects from the construction, project feasibility study, design and construction drawing design to construction, due to various reasons, the project in the declaration and approval process, some problems existing in the construction stage, these problems caused by

22、 exposure to change, and engineering cost increase. and national policies, laws and regulations and standard, the change of change, resulting in increased cost. Four, the local government of the peoples production and life convenient scheme adopted by engineering change after that cost increase. who

23、se house is caused by delay, the work of engineering change, could lead to increased cost.Highway engineering change of a variety of reasons, this means that the appraisal work for engineering changes are complex and difficult to decrease the cost, the change of the effects are also different. Throu

24、gh the analysis, is looking for engineering changes the various causes, and through the analysis of the cost control are not isolated, control cost, the key is to establish and perfect the scientific management system. Based on control cost, quality assurance and accelerate the progress, the princip

25、le of efficiency to determine the necessity and feasibility of engineering change. Only in this way can we truly achieve the effective control of the construction project cost and improve the economic benefit and social benefit.公路工程变更原因分析及其对工程造价的影响摘要:公路工程在实施阶段由于设计因素、环境因素等多方面的影响,发生工程变更是较常见的,文章结合工程实践,

26、探讨工程变更的原因及其对工程造价的影响。 关键词:工程变更;原因;造价影响 由于公路工程项目路线长、工期长、涉及面广,因此在施工中由各种原因引起的工程变更也不可避免。工程变更可能导致建设费用的增减或工期的延长,在业主和承包商之间会出现索赔和反索赔,使工程的造价发生变化。一、业主原因引起变更及其对造价的影响 1、业主改变工程招标时承诺的施工条件。如“三通一平”条件,本工程紧前项目的延迟完成等,会增加承包方的结算费用,但对总造价影响很 小;2、业主变更项目内容或项目数量。增加项目内容或者数量,会增加造价;减少或取消项目内容或数量会降低造价,但可能影响工程的使用功能;3、因业主原 因同承包方签订的协

27、议存在不完整之外,或在标段划分时出现遗漏内容,会增加合同外造价;4、业主要求提前竣工交付,缩短原合同工期,导致施工单位投入更多 的人力和物力,使造价增加;5、业主要求提高原设计标准,从安全美观等角度要求改变工程结构的型式、标高、基线、位置、尺寸、强度等,使造价增加;6、业 主要求改变已在施工组织设计中被批准的施工方案,使造价增加;7、业主对原合同中约定同业主供应的材料或设备的种类或数量进行增减,引起造价增加或减 少;8、业主的指定发包不合理,会使造价增加。 二、设计原因引起变更及其对造价的影响 1、设计采用新标准、新工艺、新技术来替代原有设计,使项目的投入使用更加有利,并为业主减少工程造价;2

28、、设计文件的深度不能满足相应设计 阶段的有关规定要求而引起的工程变更,导致造价增加或减少;3、设计单位在初步设计时未能充分考虑原地面的路网规划和地方政府及相关部门(如环境保护、供 电、供气、水利、通讯、航道等)的要求而引起的工程变更,主要表现结构形式和尺寸的改变等方面,使造价增加;4、设计人员的错误或疏漏引起工程变更。由于 “二校三审”制度落实不够导致变更使造价增加;5、设计单位设计人员之间配合不协调,或公路的附属设施同主体工程的设计不同步,引起工作变更,使造价增 加;6、分期交付的设计图纸不能及时提供,工期延误,造成施工方停工引起索赔,使造价增加。 三、承包人原因引起变更及其对造价的影响 1

29、、承包人无法履行或不能完全履行合同,承包人提出采取补救措施的变更,这类变更不能增加工程造价,由承包人负担损失费用;2、承包人变更投 标时已被批准的施工方案,这类变更对造价几乎不会产生影响,但可能为承包人节省施工费用;3、承包人为了施工方便,或为缩短工期,或为减少投入等原因,提 出对施工有利,且更加经济、合理、优化的设计方案,这类变更如果业主认可,可减少施工成本,也可降低造价,对业主和承包人双方都有利;4、承包人无法按合 同工期完成合同内容,工程可能延期,业主根据合同条款,终止全部或部分施工合同内容,改由其他承包人完成,这类变更一般不会使业主造价增加,但会使承包人 承受损失;5、由于承包人技术或

30、管理方面的失误引起工程变更,这类变更业主可以向承包人索赔,一般不增加造价;6、承包人改变合同规定由业主采购的材料, 使用其它种类型号品牌的材料,因此造成的损失由承包人承担,除非业主重新认可,一般不增加造价。 四、监理方原因引起变更及其对造价的影响 监理受业主委托,由其引起的变更费用增减直接影响业主的造价。1、监理工程师为了协调相邻标段承包人的运作,或者为了协调本工程承包人与地方 相关部门或单位的生产关系引起工程变更,容易引起造价增加。2、监理工程师针对现场的实际情况以合同和技术规范为依据,对原设计进行完善或局部修改并经设 计单位认可,这类变更可能引起造价增加。3、监理工程师工作失误和协调能力欠

31、缺造成返工损失引起工作变更,使工程造价增加。4、监理工程师提出优化设计或 优化工期,经设计认可或承包方同意引起工程变更,可降低工程造价。 五、环境因素引起变更及其对造价的影响 1、工程地质不详或不全导致设计不准确,使工程造价增加。2、公路工程建设项目从报建、工程可行性研究、初步设计、施工图设计到施工实施,由 于各种原因,项目在申报和批复过程中,存在了一些问题,这些问题在施工阶段暴露出来,引起工程变更,导致造价增加。3、国家政策、法规、规范的变化,引起 的变更,导致造价增加。4、地方政府提出的方便人民生产生活的方案被采纳后引起工程变更,使造价增加。5、征地拆迁等工作延误,所引起的工程变更,可能导 致造价的增加。 公路工程变更的原因多种多样,这就意味着工程变更的估价工作也是复杂和困难的,变更对造价增减的影响也各不相同。通过本文的分析,意是寻找 工程变更的各种原因,并通过分析说明造价控制不是孤立的,要控制好造价,关键是建立完善科学的管理体制。本着控制造价,保证质量、加快进度,提高效率的原 则来确定工程变更的必要性与可行性。只有这样才能真正达到有效控制造价,提高建设项目的经济效益和社会效益的目的。. .此处忽略!

展开阅读全文
相关资源
相关搜索
资源标签

当前位置:首页 > 学术论文 > 外文翻译(毕业设计)

版权声明:以上文章中所选用的图片及文字来源于网络以及用户投稿,由于未联系到知识产权人或未发现有关知识产权的登记,如有知识产权人并不愿意我们使用,如有侵权请立即联系:2622162128@qq.com ,我们立即下架或删除。

Copyright© 2022-2024 www.wodocx.com ,All Rights Reserved |陕ICP备19002583号-1 

陕公网安备 61072602000132号     违法和不良信息举报:0916-4228922