1、英语原文The stage of the project cost managementAbstract:Project cost management is the basic contents to determine reasonable and effective control of the project cost. Described the current stage of the project cost management situation on the strengthening of the various stages of construction cost m
2、anagement of the importance of and raised a number of key initiatives. Keywords:cost of the construction project cost management status investment decision phase of the design phase of the implementation phase of the cost management in a market economy1 preface Even under the WTO and Chinas accessio
3、n to the world community, Chinas construction industry how to effectively control construction cost of the construction and management of an important component part. However, the current budget for the construction projects - estimate, budget, Super budget accounts for the super three is still wide
4、spread and that eventually led to a serious loss of control of project investment. Project cost management is the basic contents to determine reasonable and effective control of the project cost. As the project cost to the project runs through the entire process, stage by stage can be divided into I
5、nvestment Decision stage, the design and implementation phases. The so-called Project Cost effective control is the optimization of the construction plans and design programs on the basis of in the building process at all stages, use of certain methods and measures to reduce the cost of the projects
6、 have a reasonable control on the scope and cost of the approved limits. 2 The stage of Project cost management Engineering and cost management work of the current status of project cost management system was formed in the 1950s, 1980s perfect together. Performance of the country and directly involv
7、ed in the management of economic activities. Provisions in the design stage to different estimates or budget preparation as well as government; Nothing relevant departments to formulate a budget, content, methodsand approval, the budget will provide the fixed cost of equipment and materials and fixe
8、d price of the budget preparation, approval, management authority, and so on. With the historical process, after recovery, reform and development, formed a relatively complete budget estimate of quota management system. However, as the socialist market economic development, the systems many problems
9、 have also exposed. Generally speaking, the budget estimate is based on direct participation in the management of national economic activity as a precondition. enterprise is not the actual economic entities. Due to the characteristics of the planned economy, and, at the time under the conditions of
10、productivity, will inevitably become a shortage in the economy. In severe shortage of commodities under the conditions, as long as a certain level of investment, will be certain outputs. In this environment, the project planning and technical argumentation there can be no economic analysis. State co
11、ntrol of the project cost constitute key factors equipment and materials prices, wages and taxes of artificial distribution. In this relatively stable economic environment, the budget estimate for the system approved project cost, help the government to carry out investment plans to play a major rol
12、e. As the socialist market economic system established, requires us to predict project investment and control. In recent years, international investment project developed to the requirements of prior pre-control and in the middle of control. China, the traditional practice in an objective light on t
13、he cause decision-making, implementation heavy, light the economy and technology,First, the consequences of victimization,Due to the technical personnel of the project technical and economic concepts and a weak awareness of cost control, cost management makes the quality difficult to raise. Project
14、Cost control is difficult to achieve long-term goals. Second, the various stages of the project management view of the above circumstances, My first academia in the 1980s made the whole process of cost management and control concept, building departments will study the feasibility of projects and th
15、e budgets and final accounts to two extended at the request of the corresponding regulations put our cost management concepts and methods referred to a new height. Our task now is to be modern and cost management in line with Chinas national conditions of the market economy system goal, learn from t
16、he advanced experience of the developed countries, and establish sound market economic laws of project cost management system, efforts to increase the project cost levels. An investment decision-making phase of the project cost management construction project investment decision-making stage is prop
17、osed project proposals; conduct a feasibility study to determine investment estimation and the final preparation of design task. At this stage, the projects technical and economic decision-making, of the construction project cost of the project after the completion of the economic benefits have a de
18、cisive influence, The construction cost is an important stage control. Chinas current stage of the project cost for the project management for the purpose of clearing price, and focusing only on the construction process of cost control, neglected before the start of the project investment decision-m
19、aking stage of cost control. Investment decision-making phase of investment projects is estimated an important basis for decision-making. It has a direct impact on national economic and financial analysis of the results of the reliability and accuracy. Because of this phase is the preliminary work o
20、f projects, the information can not be fully, comparable works more or less that information accumulated relatively small, estimated inadequate and unscientific. Makes project cost management and cost workers is difficult at this stage do something. The various stages of the project cost control in
21、the decision-making phase project cost control. Right project planning phase of the cost, many owners have the wrong understanding that the lower the cost the better. Cost control is not a unilateral issue, and should be a number of factors, a combination of practical, comprehensive consideration. T
22、he construction project investment decision-making stage, the projects technical and economic decision-making, Cost of the project after the completion of the project and the economic benefits, with a decisive role in project cost control is an important stage, rationally define and control the dire
23、ction of the project cost of accurate positioning and building Optimization guiding role. In the decision-making phase of the most important is to do a good job feasibility study, the work is done well, returns on investment and can form a good proportion. Otherwise, invest more, less effective, res
24、ulting in loss of control and waste of investment. At present, some of the projects planned the owners of departure from the subjective desires of a feasibility study on the lack of scientific proof. Feasibility Study untrue, false or engineering functions obtaining the approval of their superiors,
25、actually put into the feasibility study will be awarded in the study for the project after the smooth functioning buried a lot of hidden problems, lead to insufficient follow-up funds for the project and had to extend the time limit so that the project could not have planned the use of cost-effectiv
26、e, even become hopeless completion of the beard works. Therefore, in order to phase in the investment decision-making effectively control construction costs, we must do the following aspects: 1)Implementation of the construction project and corporate accountability, Construction of the project from
27、planning to implementation of the entire process and the use of the funds to repay responsibilities to the people. in addition to establishing a legal system and the project supervision matching mechanism by the departments in charge of the industry and supervision departments for setting up a monit
28、oring group to oversee the use of funds. 2)A realistic approach to market analysis, to avoid the blindness of the project decision-making, reduces and reduces investment risk. Fully consider building projects in the future market competitiveness, design task more scientific and reliability. 3) Capit
29、al financing must have a formal commitment document, the parties must do investment funds in place, and funds must have documents to ensure that the project can be approved after the scheduled implementation. To the various loan conditions should be carefully analyzed to minimize the burden of inter
30、est and repayment pressure. 4) To strengthen the engineering geology, hydrology, geology and land, water, electricity, transport, environmental projects such as external conditions for the work of depth to make the investment estimate there are sufficient grounds. Taking extensive investigation and
31、research, comparison of similar projects, seriously functional analysis, multi-program comparison and choice. After full technical appraisal and economic evaluation, and the final technologically advanced, functional and reliable. Reasonable economic projects, thus calculate a more accurate and real
32、istic estimation of the amount of investment, so that the project cost from the start positioning in a more reasonable level. 3 Design phase of the project cost control The design phase of the project cost control for a long time, Chinas building control very effective, - investment projects is not
33、uncommon, this will affect owners of investment returns, it adds to the owners and within budget, as well as difficulties in fund owners, the impact on the future management or the owners make payments in arrears, and so on. Hence, the control of the project cost is of great significance, however th
34、e project cost is the primary means of control design, Currently most of the property owners in the design stage seldom works on cost control, and they found that the cost of the design will not have a great impact, it is wrong, on the contrary, Design phase of the project cost control is the most i
35、mportant step. Because it determines engineering design, construction methods, materials and equipment types, models of the project cost is of critical significance, design optimization phase of the program or minor changes, project cost will have a significant impact, Design phase of the project co
36、st control of the total project cost of 70%. Following is how to control the project from design to create the Law: 3.1 pay attention to the design As the owners must design, the design selected on the quality level is a direct impact on the quality of product design level, and the design quality pr
37、oducts in the level of direct influence on the pricing of the works. Different design units on the same project design are different. the same item of different design institute works between certain aspects of the project cost on the existence of differences between, We assume that with a design fr
38、om two different design institute to design, Construction plans after the completion of a requested advisory unit cost to do the budget, certainly different design institute the total cost of the project is absolutely not the same, and most of the difference between the two over 10% even more than 3
39、0%, and not necessarily high cost than the design of low cost, and good design is often low cost, We all know that different people have different design styles and different levels, the design works naturally, therefore chosen to design units is the control on the first step. Through tender to sele
40、ct the design of the units is a good method, the tender documents to elaborate on this particular aspect of the requirements, cost control targets, and so on. Otherwise, in the subsequent design process design units will put an increase in the cost of the design requirements; through tendering the p
41、roject design into the market, compared to select the best design units. 3.2 Advocate design bidding and design optimization of the campaign mode design units evaluation Promoting the design bidding and design optimization campaign mode design units assessed by experts using scientific group France,
42、 in accordance with applicable, economic, aesthetic principles and advanced technology, reasonable structure to meet building energy efficiency and environmental requirements, comprehensive assessment of the merits of the program design, selection of the best determination of the successful program.
43、 Successful investment program estimated to be close to the general construction project scope of investment. This means two design contracts will help design the program of choice and competition to ensure that the selected design advanced technology, unique novelty, adaptability, as well as to con
44、trol the cost of the project. Design units should strive to improve their quality of the project design clever idea, contemporary reducing the project cost on to rack their brains to improve design quality, strive to put the design phase of the project cost control approval of the investment ceiling
45、. 3.3 Strengthening design stage Strengthening the design stage of the design phase to strengthen supervision of the Commissioner to determine a reasonable design, mature technology, reduction in the construction phase major design changes and changes in the program, in the effective control of the
46、project cost will play a role. 1 to the design of the project if the project supervision to get involved, excluding unfavorable factors may generally is excluded from the 80% errors. In the entire process of building cost control, construction began at best to save and invest 20%, the key lies in th
47、e construction phase of the identification and control costs. Supervision of the design phase include : Design Institute under the design drawings and notes help owners deal with different design options for the economy, capital expenditure to develop the preliminary estimates, to ensure that the in
48、vestment can be most effectively utilized. With the owners of the Commissioner include: According to the Design Institute to provide design drawings and notes to help owners deal with different design options for the economy, capital expenditures to develop the preliminary plan to ensure that invest
49、ment can be most effectively used; with the owners of different design options, the need to calculate their own materials and equipment to conduct a cost analysis and study, to the design staff costs, to assist them in the investment limit within limits designed to save and invest. To seek a one-time small investment and economic good design program made the most rational economic indicators. 3.4 To actively promote the so-called upper limit design Design actively promote the so-called cap limit des
版权声明:以上文章中所选用的图片及文字来源于网络以及用户投稿,由于未联系到知识产权人或未发现有关知识产权的登记,如有知识产权人并不愿意我们使用,如有侵权请立即联系:2622162128@qq.com ,我们立即下架或删除。
Copyright© 2022-2024 www.wodocx.com ,All Rights Reserved |陕ICP备19002583号-1
陕公网安备 61072602000132号 违法和不良信息举报:0916-4228922